Fire alarm maintenance and the law

In England and Wales the responsible person must make sure fire safety equipment is subject to a suitable system of maintenance and kept in an efficient state, in efficient working order and in good repair (article 17). The Order does not set intervals; BS 5839-1 is the usual measure.

The date on the last servicing certificate, or the date a new system was accepted.
Every break glass point on the system.
The day the rotation starts. Same weekday each week.
Smoke, heat and multi-sensor heads. 0 for a manual system.
From the log book.

Next service due 30 Oct 2026.

Any date from 30 Sep 2026 to 30 Nov 2026 is inside the 5 to 7 month window that BS 5839-1:2025 allows after the visit on 30 Apr 2026.

Service visits for the next two years

VisitEarliestDueLatestAlso at this visit
130 Sep 202630 Oct 202630 Nov 2026ARC signals, panel clock, false alarm rate
230 Mar 202730 Apr 202730 May 202712 months on: duct smoke detectors
330 Sep 202730 Oct 202730 Nov 2027ARC signals, panel clock, false alarm rate
430 Mar 202830 Apr 202830 May 202812 months on: duct smoke detectors

Assumes each visit happens on its due date. If your last visit was not a 12-monthly one, the 12-monthly items fall on visits 1 and 3 instead. Every visit checks ARC signals, the panel clock and the false alarm rate.

Weekly call point rotation

With 12 call points, each one is operated once every 12 weeks, so about 4.3 times a year by the weekly test alone.

WeekDateCall pointResultSignature
1Mon 23 Nov 2026CP 1
2Mon 30 Nov 2026CP 2
3Mon 7 Dec 2026CP 3
4Mon 14 Dec 2026CP 4
5Mon 21 Dec 2026CP 5
6Mon 28 Dec 2026CP 6
7Mon 4 Jan 2027CP 7
8Mon 11 Jan 2027CP 8
9Mon 18 Jan 2027CP 9
10Mon 25 Jan 2027CP 10
11Mon 1 Feb 2027CP 11
12Mon 8 Feb 2027CP 12

False alarm rate

1 / 40 x 100 = 2.5 false alarms per 100 detectors per year. Under 4 per 100. The servicing engineer still checks the rate at every visit.

Runs in your browser; nothing you type is sent anywhere. England and Wales.

What a fire risk assessment checks

The government's fire risk assessment checklist asks whether weekly testing and periodic maintenance routines are in place for the fire alarm, and whether records are kept. A service schedule for a visit on 30 Apr 2026:

After 30 Apr 2026EarliestDueLatest
Visit 130 Sep 202630 Oct 202630 Nov 2026
Visit 230 Mar 202730 Apr 202730 May 2027

Scotland and Northern Ireland

Different legislation applies there. This site covers England and Wales.

Before you rely on these dates

Questions

Can the responsible person hand the testing to someone else?

They can delegate tasks like the weekly test, but the duty stays theirs.

Related

A service register for every site you look after

We are building a register for fire alarm engineers and building managers: every site's service dates and windows, weekly test rotations and false alarm rates in one place, with a reminder before a visit falls outside its window. Planned price £39 a month. Join the waitlist and we will email you when it opens. Nothing to pay now.