Fire Alarm RegisterAll guides

When a fire alarm service is missed

A visit up to 7 months after the last one is inside the 2025 allowance. Past that, book the service, note why it was late in the log book, and bring later dates back towards the original schedule.

The date on the last servicing certificate, or the date a new system was accepted.
Every break glass point on the system.
The day the rotation starts. Same weekday each week.
Smoke, heat and multi-sensor heads. 0 for a manual system.
From the log book.

Next service due 10 Aug 2026.

Any date from 10 Jul 2026 to 10 Sep 2026 is inside the 5 to 7 month window that BS 5839-1:2025 allows after the visit on 10 Feb 2026.

Service visits for the next two years

VisitEarliestDueLatestAlso at this visit
110 Jul 202610 Aug 202610 Sep 2026ARC signals, panel clock, false alarm rate
210 Jan 202710 Feb 202710 Mar 202712 months on: duct smoke detectors
310 Jul 202710 Aug 202710 Sep 2027ARC signals, panel clock, false alarm rate
410 Jan 202810 Feb 202810 Mar 202812 months on: duct smoke detectors

Assumes each visit happens on its due date. If your last visit was not a 12-monthly one, the 12-monthly items fall on visits 1 and 3 instead. Every visit checks ARC signals, the panel clock and the false alarm rate.

Weekly call point rotation

With 12 call points, each one is operated once every 12 weeks, so about 4.3 times a year by the weekly test alone.

WeekDateCall pointResultSignature
1Mon 23 Nov 2026CP 1
2Mon 30 Nov 2026CP 2
3Mon 7 Dec 2026CP 3
4Mon 14 Dec 2026CP 4
5Mon 21 Dec 2026CP 5
6Mon 28 Dec 2026CP 6
7Mon 4 Jan 2027CP 7
8Mon 11 Jan 2027CP 8
9Mon 18 Jan 2027CP 9
10Mon 25 Jan 2027CP 10
11Mon 1 Feb 2027CP 11
12Mon 8 Feb 2027CP 12

False alarm rate

1 / 40 x 100 = 2.5 false alarms per 100 detectors per year. Under 4 per 100. The servicing engineer still checks the rate at every visit.

Runs in your browser; nothing you type is sent anywhere. England and Wales.

Example

Last service 10 Feb 2026. Due 10 Aug 2026, latest 10 Sep 2026. A visit after 10 Sep 2026 is outside the window.

After 10 Feb 2026EarliestDueLatest
Visit 110 Jul 202610 Aug 202610 Sep 2026
Visit 210 Jan 202710 Feb 202710 Mar 2027

Why it matters

The Regulatory Reform (Fire Safety) Order 2005 requires fire safety equipment to be subject to a suitable system of maintenance (article 17), and the government's fire risk assessment checklist asks whether weekly testing and periodic maintenance routines are in place and recorded. See the law.

Before you rely on these dates

Questions

Is a late service illegal?

The law asks for a suitable system of maintenance; it does not name a number of months. BS 5839-1 is the usual measure of what is suitable.

Related

A service register for every site you look after

We are building a register for fire alarm engineers and building managers: every site's service dates and windows, weekly test rotations and false alarm rates in one place, with a reminder before a visit falls outside its window. Planned price £39 a month. Join the waitlist and we will email you when it opens. Nothing to pay now.